Project:
Rothmühle (DE) – Biogas plant
Process area:
Digestion, Pasteurization, Pre-Treatment, Pumps, Top
Charging material:
• 25,000 t/a
• Municipal garden waste
• Organic waste and commercial kitchen waste
FINSTERWALDER work packages
2019
- Machine delivery
- Installation
- Commissioning
2014
- Approval planning
- Process diagram & constructionTurnkey delivery of a wet fermentation system 18,000 t/year
FINSTERWALDER machines used
- Separation press BS20
- Ball valve pump KV20
- Pasteurization system
- Floor scraper
- Sediment separator
- Skimmer
Year 2014/2019
FINSTERWALDER Environmental Technology
Similar projects
Our technology offers individual solutions for all process areas in the field of biogas and anaerobic digestion of organic waste. We support our customers from the initial idea through to planning, implementation, commissioning and ongoing operation. Similar projects of our worldwide customers can be found here!
Biology
Moosburg – Sewage treatment plant (DE)
Charging material:
• 75 m³/d Centrate from sewage sludge
• Leftovers
Langage Farm AD – Biogas plant (United Kingdom)
Charging material:
• 18,000 tons/year of kitchen waste
• Fertilize
Pasteurization, Pumps
Windmill Holsteins Farms (CA) – Biogas plant
Charging material:
• 7,500 t/a
• Organic waste
Biology, Case Studies, Digestion, Pasteurization, Pre-Treatment, Pumps
Biopower Bernau (DE) – The own biogas plant, test plant
Charging material:
• 6,000 t/a
• Commercial food waste
• Municipal waste
Digestion, Pre-Treatment
Buchholz biogas plant (LU – treatment plant
Charging material:
• 7,550 t/a
• agricultural substrates