Project details
Project:
Langage Farm AD – Biogas plant (United Kingdom)
Process area:
unknown
Charging material:
โข 18,000 tons/year of kitchen waste
โข Fertilize
FINSTERWALDER work packages
- Process diagram & construction
- Machine delivery
- PLC programming
- Commissioning
FINSTERWALDER machines used
- Double-tube heat exchanger
- 3x floor scraper
- Sediment separator
- 3x skimmer
Similar projects
Our technology offers individual solutions for all process areas in the field of biogas and anaerobic digestion of organic waste. We support our customers from the initial idea through to planning, implementation, commissioning and ongoing operation. Similar projects of our worldwide customers can be found here!
Digestion, Pre-Treatment, Pumps
Xian (CN) – Digestion plant for organic waste
Charging material:
โข 400 t/d
โข Food waste and municipal biowaste
Case Studies
Biogas plant URUMQI (CN) – Planning biogas plant
Charging material:
โข 300 t/day of kitchen wast

Biology, Pasteurization, Pumps
Villa Avocado (MX) – Biogas plant
Charging material:
โข 43,000 t/d
โข Organic waste from avocado oil production process
Digestion, Pre-Treatment
Bioenergy Schlitters (AT) – Waste pre-treatment and sediment discharge
Charging material:
โข 10,000 t/a
โข Commercial food waste
โข Municipal waste
Pre-Treatment, Pumps
Davidson Environmental (CA) – Compact treatment
Charging material:
โข 12,000 t/a
โข Commercial kitchen waste