Project details
Project:
Langage Farm AD – Biogas plant (United Kingdom)
Process area:
unknown
Charging material:
• 18,000 tons/year of kitchen waste
• Fertilize
FINSTERWALDER work packages
- Process diagram & construction
- Machine delivery
- PLC programming
- Commissioning
FINSTERWALDER machines used
- Double-tube heat exchanger
- 3x floor scraper
- Sediment separator
- 3x skimmer
Similar projects
Our technology offers individual solutions for all process areas in the field of biogas and anaerobic digestion of organic waste. We support our customers from the initial idea through to planning, implementation, commissioning and ongoing operation. Similar projects of our worldwide customers can be found here!
Biology
Moosburg – Sewage treatment plant (DE)
Charging material:
• 75 m³/d Centrate from sewage sludge
• LeftoversBiology, Digestion, Pre-Treatment
Jiangjin (CN) – Treatment plant and fermentation
Charging material:
• 75,000 t/a
• Contaminated kitchen wastePumps
Anröchte (DE) – Pump system with high solids content
Charging material: