Project details

Project:

Yongjia (CN) – Food waste digestion plant

Process area:

Digestion, Pre-Treatment, Pumps

Charging material:

• 36,500 t/a
• Commercial kitchen waste from the catering industry

FINSTERWALDER work packages

  • Process diagram & construction support
  • Machine delivery
  • Remote commissioning

FINSTERWALDER machines used

  • Gate valve pump KS23
  • Separation press BS20
  • Gate valve pump KP10
  • Floor scraper
  • Skimmer
  • Pressure/vacuum relief valve

Year 2020

FITEC China

Project planning, waste consulting, individual solutions

We are professionals and can help you!

Based on detailed raw material data, we design customized solutions to meet your needs. Modernization of existing systems is just one of our strengths!

Project planning, waste consulting, individual solutions

We are professionals and can help you!

Based on detailed raw material data, we design customized solutions to meet your needs. Modernization of existing systems is just one of our strengths!

Similar projects

Our technology offers individual solutions for all process areas in the field of biogas and anaerobic digestion of organic waste. We support our customers from the initial idea through to planning, implementation, commissioning and ongoing operation. Similar projects of our worldwide customers can be found here!

  • Pasteurization, Pumps

    Windmill Holsteins Farms (CA) – Biogas plant

    Charging material:

    • 7,500 t/a
    • Organic waste

  • Biology, Digestion, Pasteurization, Pre-Treatment, Pumps

    EcoCenter Lana (IT) – Biogas plant

    Charging material:

    • 32,000 t/a
    • Municipal organic waste and food waste

  • Digestion

    KBA Hard (CH) – Sediment discharge system

    Charging material:

    • Leftovers

  • Digestion, Pasteurization, Pumps

    Escarpment Renewables (CA) – Modernization of biogas plant

    Charging material:

    • 35,000 t/a
    • Commercial kitchen waste

  • Digestion, Pre-Treatment, Pumps

    Xian (CN) – Digestion plant for organic waste

    Charging material:

    • 400 t/d
    • Food waste and municipal biowaste