Project details
Project:
Xiqing (CN) – Pre-treatment system for food waste
Process area:
Pre-Treatment, Pumps
Charging material:
• 76,000 t/a
• Commercial food waste
FINSTERWALDER work packages
- Process diagram & construction support
- Machine delivery
- Remote commissioning
FINSTERWALDER machines used
- Separation press BS20
- Gate valve pump KS23
- Gate valve pump KP10
Year 2019
Similar projects
Our technology offers individual solutions for all process areas in the field of biogas and anaerobic digestion of organic waste. We support our customers from the initial idea through to planning, implementation, commissioning and ongoing operation. Similar projects of our worldwide customers can be found here!
Biology, Pasteurization, Pumps
Villa Avocado (MX) – Biogas plant
Charging material:
• 43,000 t/d
• Organic waste from avocado oil production process
Case Studies
Rothmühle AES GmbH (DE) – Planning of wet fermentation plant
Charging material:
• 32,000 t/a
• Municipal organic waste and food waste
Biology, Digestion, Pasteurization, Pumps
Maryland Biogas (CA) – Biogas plant
Charging material:
• 15,000 t/a
• Municipal organic waste
Biology, Case Studies, Digestion, Pasteurization, Pre-Treatment, Pumps
Biopower Bernau (DE) – The own biogas plant, test plant
Charging material:
• 6,000 t/a
• Commercial food waste
• Municipal waste
Pre-Treatment, Pumps
Davidson Environmental (CA) – Compact treatment
Charging material:
• 12,000 t/a
• Commercial kitchen waste