Project details
Project:
Xiqing (CN) – Pre-treatment system for food waste
Process area:
Pre-Treatment, Pumps
Charging material:
• 76,000 t/a
• Commercial food waste
FINSTERWALDER work packages
- Process diagram & construction support
- Machine delivery
- Remote commissioning
FINSTERWALDER machines used
- Separation press BS20
- Gate valve pump KS23
- Gate valve pump KP10
Year 2019
Similar projects
Our technology offers individual solutions for all process areas in the field of biogas and anaerobic digestion of organic waste. We support our customers from the initial idea through to planning, implementation, commissioning and ongoing operation. Similar projects of our worldwide customers can be found here!
Langage Farm AD – Biogas plant (United Kingdom)
Charging material:
• 18,000 tons/year of kitchen waste
• Fertilize
Digestion, Pasteurization, Pre-Treatment, Pumps
BAVA Garmisch-Partenkirchen (DE) – Biogas plant
Charging material:
• 10,000 t/a
• Municipal organic waste and food waste
Pre-Treatment, Pumps
Xiqing (CN) – Pre-treatment system for food waste
Charging material:
• 76,000 t/a
• Commercial food waste