Project details
Project:
Xian (CN) – Digestion plant for organic waste
Process area:
Digestion, Pre-Treatment, Pumps
Charging material:
• 400 t/d
• Food waste and municipal biowaste
FINSTERWALDER work packages
- Machine delivery
- Design Support
- Commissioning support
FINSTERWALDER machines used
- Separation press BS20
- Gate valve pump KS23
- Hydraulic unit for KS23
- Lightweight skimmer
- Floor scraper
Year 2023
FITEC China
Similar projects
Our technology offers individual solutions for all process areas in the field of biogas and anaerobic digestion of organic waste. We support our customers from the initial idea through to planning, implementation, commissioning and ongoing operation. Similar projects of our worldwide customers can be found here!
Digestion, Pasteurization, Pre-Treatment, Pumps, Top
Rothmühle (DE) – Biogas plant
Charging material:
• 25,000 t/a
• Municipal garden waste
• Organic waste and commercial kitchen waste
Biology
Moosburg – Sewage treatment plant (DE)
Charging material:
• 75 m³/d Centrate from sewage sludge
• Leftovers
Digestion, Pre-Treatment, Pumps
Urumqi (CN) – Biogas plant for organic waste
Charging material:
• 109,500 t/a

Digestion, Pre-Treatment
Bioenergy Schlitters (AT) – Waste pre-treatment and sediment discharge
Charging material:
• 10,000 t/a
• Commercial food waste
• Municipal waste
Biology, Pasteurization, Pumps
Villa Avocado (MX) – Biogas plant
Charging material:
• 43,000 t/d
• Organic waste from avocado oil production process