Project details
Project:
Urumqi (CN) – Biogas plant for organic waste
Process area:
Digestion, Pre-Treatment, Pumps
Charging material:
• 109,500 t/a
FINSTERWALDER work packages
- Machine delivery
- Commissioning support
FINSTERWALDER machines used
- Gate valve pump KS23
- Ball valve pump KV20
- Separation press BS20
- Floor scraper
- Skimmer
- Sediment carrier
Year 2021
FITEC China
Similar projects
Our technology offers individual solutions for all process areas in the field of biogas and anaerobic digestion of organic waste. We support our customers from the initial idea through to planning, implementation, commissioning and ongoing operation. Similar projects of our worldwide customers can be found here!
Case Studies
EcoCenter Lana (IT) – Revision of hydrolysis
Charging material:
• 32,000 t/a
• Municipal organic waste and food waste
Biology, Digestion, Pre-Treatment
Jiangjin (CN) – Treatment plant and fermentation
Charging material:
• 75,000 t/a
• Contaminated kitchen waste
Case Studies
Composting plant Anröchte – Pumping technology
Charging material:
- unknown