Project details
Project:
Urumqi (CN) – Biogas plant for organic waste
Process area:
Digestion, Pre-Treatment, Pumps
Charging material:
• 109,500 t/a
FINSTERWALDER work packages
- Machine delivery
- Commissioning support
FINSTERWALDER machines used
- Gate valve pump KS23
- Ball valve pump KV20
- Separation press BS20
- Floor scraper
- Skimmer
- Sediment carrier
Year 2021
FITEC China
Similar projects
Our technology offers individual solutions for all process areas in the field of biogas and anaerobic digestion of organic waste. We support our customers from the initial idea through to planning, implementation, commissioning and ongoing operation. Similar projects of our worldwide customers can be found here!
Digestion
Ovobrand (AR) – system for sediment separation
Charging material:
• 120 t/d
• Chicken litteDigestion, Pasteurization, Pre-Treatment, Pumps
Langage Farm AD (UK) – Equipment for substrate cleaning
Charging material:
• 18,000 t/a
• Kitchen waste from the catering tradeBiology, Digestion, Pasteurization, Pre-Treatment, Pumps
EcoCenter Lana (IT) – Biogas plant
Charging material:
• 32,000 t/a
• Municipal organic waste and food waste