Project details
Project:
Urumqi (CN) – Biogas plant for organic waste
Process area:
Digestion, Pre-Treatment, Pumps
Charging material:
• 109,500 t/a
FINSTERWALDER work packages
- Machine delivery
- Commissioning support
FINSTERWALDER machines used
- Gate valve pump KS23
- Ball valve pump KV20
- Separation press BS20
- Floor scraper
- Skimmer
- Sediment carrier
Year 2021
FITEC China
Similar projects
Our technology offers individual solutions for all process areas in the field of biogas and anaerobic digestion of organic waste. We support our customers from the initial idea through to planning, implementation, commissioning and ongoing operation. Similar projects of our worldwide customers can be found here!
Digestion, Pasteurization, Pre-Treatment, Pumps, Top
Rothmühle (DE) – Biogas plant
Charging material:
• 25,000 t/a
• Municipal garden waste
• Organic waste and commercial kitchen waste
Digestion, Pre-Treatment
Bioenergy Schlitters (AT) – Waste pre-treatment and sediment discharge
Charging material:
• 10,000 t/a
• Commercial food waste
• Municipal waste
Pasteurization, Pre-Treatment, Pumps, Top
Entsorgungsbetriebe Lübeck (DE) – Processing of food waste
Charging material:
• 5,000 t/a
• Food waste and municipal biowaste