Project details
Project:
Langage Farm AD (UK) – Equipment for substrate cleaning
Process area:
Digestion, Pasteurization, Pre-Treatment, Pumps
Charging material:
โข 18,000 t/a
โข Kitchen waste from the catering trade
FINSTERWALDER work packages
- Process planning
- Machine delivery
- PLC programming
- Commissioning
FINSTERWALDER machines used
- Ball valve pump KV20
- Separation press BS20
- Hydraulic power unit
- Double-tube heat exchanger
- Floor scraper
- Sediment separator
- Skimmer
Year 2011/2015/2023
FINSTERWALDER Environmental Technology
Similar projects
Our technology offers individual solutions for all process areas in the field of biogas and anaerobic digestion of organic waste. We support our customers from the initial idea through to planning, implementation, commissioning and ongoing operation. Similar projects of our worldwide customers can be found here!
Biology, Digestion, Pre-Treatment
Jiangjin (CN) – Treatment plant and fermentation
Charging material:
โข 75,000 t/a
โข Contaminated kitchen waste
Case Studies
EcoCenter Lana (IT) – Revision of hydrolysis
Charging material:
โข 32,000 t/a
โข Municipal organic waste and food waste
Digestion, Pre-Treatment
Buchholz biogas plant (LU – treatment plant
Charging material:
โข 7,550 t/a
โข agricultural substrates
โข Food waste and organic waste
Digestion, Pre-Treatment
Buchholz biogas plant (LU – treatment plant
Charging material:
โข 7,550 t/a
โข agricultural substrates
โข Food waste and organic waste
Digestion, Pre-Treatment, Pumps
Yongjia (CN) – Food waste digestion plant
Charging material:
โข 36,500 t/a
โข Commercial kitchen waste from the catering industry