Project details

Project:

Langage Farm AD – Biogas plant (United Kingdom)

Process area:

unknown

Charging material:

• 18,000 tons/year of kitchen waste
• Fertilize

FINSTERWALDER work packages

  • Process diagram & construction
  • Machine delivery
  • PLC programming
  • Commissioning

FINSTERWALDER machines used

  • Double-tube heat exchanger
  • 3x floor scraper
  • Sediment separator
  • 3x skimmer

Project planning, waste consulting service, customized solutions

We are professionals and can help you!

Based on detailed raw material data, we design customized solutions to meet your needs. Modernization of existing systems is just one of our strengths!

Project planning, waste consulting, individual solutions

We are professionals and can help you!

Based on detailed raw material data, we design customized solutions to meet your needs. Modernization of existing systems is just one of our strengths!

Similar projects

Our technology offers individual solutions for all process areas in the field of biogas and anaerobic digestion of organic waste. We support our customers from the initial idea through to planning, implementation, commissioning and ongoing operation. Similar projects of our worldwide customers can be found here!

  • Digestion

    KBA Hard (CH) – Sediment discharge system

    Charging material:

    • Leftovers

  • Langage Farm AD – Biogas plant (United Kingdom)

    Charging material:

    • 18,000 tons/year of kitchen waste
    • Fertilize

  • Digestion, Pre-Treatment, Pumps

    Xian (CN) – Digestion plant for organic waste

    Charging material:

    • 400 t/d
    • Food waste and municipal biowaste

  • Case Studies

    Rothmühle AES GmbH (DE) – Planning of wet fermentation plant

    Charging material:

    • 32,000 t/a
    • Municipal organic waste and food waste

  • Digestion, Pre-Treatment, Pumps

    Urumqi (CN) – Biogas plant for organic waste

    Charging material:

    • 109,500 t/a