Project:

KBA Hard (CH) – Sediment discharge system

Process area:

Digestion

Charging material:

• Leftovers

FINSTERWALDER work packages

  • Machine delivery
  • Commissioning

FINSTERWALDER machines used

  • Floor-operated floor scraper

Year 2015

FINSTERWALDER Environmental Technology

Project planning, waste consulting service, customized solutions

We are professionals and can help you!

Based on detailed raw material data, we design customized solutions to meet your needs. Modernization of existing systems is just one of our strengths!

Project planning, waste consulting, individual solutions

We are professionals and can help you!

Based on detailed raw material data, we design customized solutions to meet your needs. Modernization of existing systems is just one of our strengths!

Similar projects

Our technology offers individual solutions for all process areas in the field of biogas and anaerobic digestion of organic waste. We support our customers from the initial idea through to planning, implementation, commissioning and ongoing operation. Similar projects of our worldwide customers can be found here!

  • Case Studies

    EcoCenter Lana (IT) – Revision of hydrolysis

    Charging material:

    • 32,000 t/a
    • Municipal organic waste and food waste

    Lana EcoCenter, Revision der Hydrolyse
  • Digestion, Pre-Treatment, Pumps

    Urumqi (CN) – Biogas plant for organic waste

    Charging material:

    • 109,500 t/a

  • Langage Farm AD – Biogas plant (United Kingdom)

    Charging material:

    • 18,000 tons/year of kitchen waste
    • Fertilize

  • Digestion, Pasteurization, Pre-Treatment, Pumps

    Langage Farm AD (UK) – Equipment for substrate cleaning

    Charging material:

    • 18,000 t/a
    • Kitchen waste from the catering trade

  • Biology

    Moosburg – Sewage treatment plant (DE)

    Charging material:

    • 75 m³/d Centrate from sewage sludge
    • Leftovers