Project details
Project:
EcoCenter Lana (IT) – Biogas plant
Process area:
Biology, Digestion, Pasteurization, Pre-Treatment, Pumps
Charging material:
• 32,000 t/a
• Municipal organic waste and food waste
FINSTERWALDER work packages
- Process diagram & construction
- Machine delivery
- Installation
- Commissioning
- LPH 1-3 according to HOAI
FINSTERWALDER machines used
- Ball valve pump KV20
- Double-tube heat exchanger for digester heating
- Floor scraper
- Sediment separator
- Skimmer
- Bicarbonate tester
Year 2018
FINSTERWALDER Environmental Technology
Similar projects
Our technology offers individual solutions for all process areas in the field of biogas and anaerobic digestion of organic waste. We support our customers from the initial idea through to planning, implementation, commissioning and ongoing operation. Similar projects of our worldwide customers can be found here!
Biology
Moosburg – Sewage treatment plant (DE)
Charging material:
• 75 m³/d Centrate from sewage sludge
• LeftoversDigestion, Pre-Treatment
Bioenergy Schlitters (AT) – Waste pre-treatment and sediment discharge
Charging material:
• 10,000 t/a
• Commercial food waste
• Municipal wasteDigestion, Pasteurization, Pre-Treatment, Pumps, Top
Rothmühle (DE) – Biogas plant
Charging material:
• 25,000 t/a
• Municipal garden waste
• Organic waste and commercial kitchen waste
Digestion, Pasteurization, Pre-Treatment, Pumps
Bioenergie Kaiserwinkel (AT) – Biogas plant
Charging material:
• 5,000 t/a
• Leftovers from the catering trade
• Municipal wasteDigestion, Pasteurization, Pumps
Courthouse Hill Farms – Biogas plant (CA)
Charging material:
• 15,000 t/a
• Municipal organic waste