Project details
Project:
Bayview Biogas (CA) – Hygienization and discharge system
Process area:
Biology, Digestion, Pasteurization
Charging material:
• 6,000 t/a
• Grape marc and food waste
FINSTERWALDER work packages
- Process diagram & construction
- Machine delivery
FINSTERWALDER machines used
- Double-tube heat exchanger
- Bicarbonate analyzer APAS
- Skimmer
Year 2015
FITEC North America
Similar projects
Our technology offers individual solutions for all process areas in the field of biogas and anaerobic digestion of organic waste. We support our customers from the initial idea through to planning, implementation, commissioning and ongoing operation. Similar projects of our worldwide customers can be found here!
Digestion, Pre-Treatment, Pumps
Yongjia (CN) – Food waste digestion plant
Charging material:
• 36,500 t/a
• Commercial kitchen waste from the catering industryLangage Farm AD – Biogas plant (United Kingdom)
Charging material:
• 18,000 tons/year of kitchen waste
• FertilizePasteurization, Pumps
Windmill Holsteins Farms (CA) – Biogas plant
Charging material:
• 7,500 t/a
• Organic waste
Digestion, Pasteurization, Pre-Treatment, Pumps, Top
Rothmühle (DE) – Biogas plant
Charging material:
• 25,000 t/a
• Municipal garden waste
• Organic waste and commercial kitchen wastePasteurization, Pre-Treatment, Pumps, Top
Entsorgungsbetriebe Lübeck (DE) – Processing of food waste
Charging material:
• 5,000 t/a
• Food waste and municipal biowaste