Project details
Project:
Anröchte (DE) – Pump system with high solids content
Process area:
Pumps
Charging material:
• Digestate from dry fermentation
FINSTERWALDER work packages
- Machine delivery
- Installation
- Commissioning
FINSTERWALDER machines used
- Gate valve pump KS23 (Digestate circulation pump TS~25%)
- Hydraulic unit 37.5kW
Year 2019
FINSTERWALDER Environmental Technology
Similar projects
Our technology offers individual solutions for all process areas in the field of biogas and anaerobic digestion of organic waste. We support our customers from the initial idea through to planning, implementation, commissioning and ongoing operation. Similar projects of our worldwide customers can be found here!
Biology, Pasteurization, Pumps
Villa Avocado (MX) – Biogas plant
Charging material:
• 43,000 t/d
• Organic waste from avocado oil production processDigestion, Pre-Treatment
Buchholz biogas plant (LU – treatment plant
Charging material:
• 7,550 t/a
• agricultural substrates
• Food waste and organic wasteDigestion
Ovobrand (AR) – system for sediment separation
Charging material:
• 120 t/d
• Chicken litte