Project details
Project:
Anröchte (DE) – Pump system with high solids content
Process area:
Pumps
Charging material:
• Digestate from dry fermentation
FINSTERWALDER work packages
- Machine delivery
- Installation
- Commissioning
FINSTERWALDER machines used
- Gate valve pump KS23 (Digestate circulation pump TS~25%)
- Hydraulic unit 37.5kW
Year 2019
FINSTERWALDER Environmental Technology
Similar projects
Our technology offers individual solutions for all process areas in the field of biogas and anaerobic digestion of organic waste. We support our customers from the initial idea through to planning, implementation, commissioning and ongoing operation. Similar projects of our worldwide customers can be found here!
Digestion, Pasteurization, Pre-Treatment, Pumps
Bioenergie Kaiserwinkel (AT) – Biogas plant
Charging material:
• 5,000 t/a
• Leftovers from the catering trade
• Municipal wasteCase Studies, Digestion, Pasteurization, Pre-Treatment, Pumps
BAVA Garmisch-Partenkirchen (DE) – Biogas plant
Charging material:
• 10,000 t/a
• Municipal organic waste and food wasteDigestion, Pasteurization, Pre-Treatment, Pumps, Top
Rothmühle (DE) – Biogas plant
Charging material:
• 25,000 t/a
• Municipal garden waste
• Organic waste and commercial kitchen waste