Project details
Project:
Villa Avocado (MX) – Biogas plant
Process area:
Biology, Pasteurization, Pumps
Charging material:
• 43,000 t/d
• Organic waste from avocado oil production process
FINSTERWALDER work packages
- Design LPH 1-3 according to HOAI
FINSTERWALDER machines used
- Ball valve pump KV20
- Double-tube heat exchanger
- Bicarbonate analyzer
Year 2023
FITEC North America
Similar projects
Our technology offers individual solutions for all process areas in the field of biogas and anaerobic digestion of organic waste. We support our customers from the initial idea through to planning, implementation, commissioning and ongoing operation. Similar projects of our worldwide customers can be found here!
Case Studies, Digestion, Pasteurization, Pre-Treatment, Pumps
BAVA Garmisch-Partenkirchen (DE) – Biogas plant
Charging material:
• 10,000 t/a
• Municipal organic waste and food wasteDigestion, Pre-Treatment, Pumps
Xian (CN) – Digestion plant for organic waste
Charging material:
• 400 t/d
• Food waste and municipal biowasteDigestion, Pre-Treatment, Pumps
Urumqi (CN) – Biogas plant for organic waste
Charging material:
• 109,500 t/a
Biology, Digestion, Pasteurization, Pre-Treatment, Pumps
EcoCenter Lana (IT) – Biogas plant
Charging material:
• 32,000 t/a
• Municipal organic waste and food wasteDigestion, Pasteurization, Pre-Treatment, Pumps
Bioenergie Kaiserwinkel (AT) – Biogas plant
Charging material:
• 5,000 t/a
• Leftovers from the catering trade
• Municipal waste