Project:
Xiqing (CN) – Pre-treatment system for food waste
Process area:
Pre-Treatment, Pumps
Charging material:
• 76,000 t/a
• Commercial food waste
FINSTERWALDER work packages
- Process diagram & construction support
- Machine delivery
- Remote commissioning
FINSTERWALDER machines used
- Separation press BS20
- Gate valve pump KS23
- Gate valve pump KP10
Year 2019
Similar projects
Our technology offers individual solutions for all process areas in the field of biogas and anaerobic digestion of organic waste. We support our customers from the initial idea through to planning, implementation, commissioning and ongoing operation. Similar projects of our worldwide customers can be found here!
Case Studies
Rothmühle AES GmbH (DE) – Planning of wet fermentation plant
Charging material:
• 32,000 t/a
• Municipal organic waste and food waste
Digestion, Pumps
Little Island, Cork (IE) – Sediment removal and skimmer system
Charging material:
• 90.000 t/y
• domestic andcommercial food waste
Digestion, Pre-Treatment, Pumps
Yongjia (CN) – Food waste digestion plant
Charging material:
• 36,500 t/a
• Commercial kitchen waste from the catering industry